FGSD 2022 Bond » Harvey Clarke Elementary Building Addition (2025-2026)

Harvey Clarke Elementary Building Addition (2025-2026)

Construction of the building addition (at the rear of the school) began in October 2025 and was substantially completed at the end of May 2026. The addition includes a pre-K and second classroom as well as new student restrooms. Furniture, toilet partitions and repaving of the courtyard area will be completed by the end of summer. Old student restrooms in the library hallway are being converted into staff restrooms.