Harvey Clarke Elementary Building Addition (2025-2026)
Construction of the building addition (at the rear of the school) began in October 2025 and was substantially completed at the end of May 2026. The addition includes a pre-K and second classroom as well as new student restrooms. Furniture, toilet partitions and repaving of the courtyard area will be completed by the end of summer. Old student restrooms in the library hallway are being converted into staff restrooms.
Renderings of Pre-K Addition
June 22, 2026
June 17, 2026 - Renovations of Nearby Restrooms
June 4, 2026 - Partitions Added in New Restrooms
May 11, 2026
May 6, 2026
April 27, 2026
April 17, 2026
April 10, 2026
April 2, 2026
March 27, 2026
March 18, 2026
March 9, 2026
Feb. 19, 2026
Feb. 12, 2026
Jan. 15, 2026 - Building Framed
Nov. 25, 2025 - Concrete Foundation Poured
Nov. 11, 2025 - Addition Perimeter Constructed
Oct. 28, 2025 - Construction Begins on Building Addition