Dilley Elementary Phase 2 (2025-2026)
Projects completed in summer and fall 2025 included:
- Renovate existing classroom for pre-K use
- Classroom technology
- New play structure
- HVAC unit upgrades
Coming in 2026:
- Classroom addition (1198 sq ft)
- New garden area and planters
2025 Construction Plans
Dec. 10, 2025 - Old Garden Area Removed
Nov. 12, 2025 - Installation of HVAC Rooftop Units
Aug. 29, 2025
Aug. 21, 2025 - Adding Finishing Touches
Aug. 13, 2025
July 30, 2025 - Play Structure Installation Begins
July 23, 2025
July 16, 2025
July 7, 2025
July 1, 2025 - Playground Site Graded, Trenching for Pre-K Classroom
June 26, 2025 - Pre-K Classroom Construction, Playground Progress
June 19, 2025 - Removal of Old Playground Begins