Neil Armstrong MS Track, Field, Covered PE Area (2024-2025)
Architect's Rendering - Outdoor PE Area
Sept. 3, 2024 - Canopy, Hoops Added
Aug. 27, 2024 - Paint, Asphalt
Aug. 20, 2024 - Priming PE Structure
Aug. 14, 2024 - Sandblasting Covered PE Structure
July 31, 2024 - Field Work Completed, Covered PE Structure Erected
July 22, 2024 - Finishing Field, Footings for Covered PE Area
July 16, 2024 - Constructing Forms for Covered Play Footings
July 10-13, 2024 - Final Striping, Addition of Rubberized Pellets
June 28-July 3, 2024 - Synthetic Turf Field Installation (VIDEO)
June 18, 2024 - Field Work, Covered PE Area
June 12, 2024 - Field Drainage Work
June 5, 2024 - Compaction and Filling Continue
May 29, 2024 - Continued Field Work
May 22, 2024 - Installation of Drainage
May 14, 2024 - Cement Treatment Begins
May 7, 2024 - Excavation of Field Area